http://hl7.org/fhir/action-relationship-type|4.0.1
name
ActionRelationshipType
ActionRelationshipType
package
hl7.fhir.r4.core@4.0.1
hl7.fhir.r4.core@4.0.1
content
complete
complete
status
draft
draft
date
2019-10-31 22:29:23.0
2019-10-31 22:29:23.0
ActionRelationshipType
Defines the types of relationships between actions.
| code | display | definition | hierarchy |
|---|---|---|---|
| before-start | Before Start | The action must be performed before the start of the related action.... | |
| before | Before | The action must be performed before the related action.... | |
| before-end | Before End | The action must be performed before the end of the related action.... | |
| concurrent-with-start | Concurrent With Start | The action must be performed concurrent with the start of the related action.... | |
| concurrent | Concurrent | The action must be performed concurrent with the related action.... | |
| concurrent-with-end | Concurrent With End | The action must be performed concurrent with the end of the related action.... | |
| after-start | After Start | The action must be performed after the start of the related action.... | |
| after | After | The action must be performed after the related action.... | |
| after-end | After End | The action must be performed after the end of the related action.... |